Replacing failed GRP with a completely rebuilt lead roof system

This Scottish Borders project involved two projecting bay roofs that had originally been finished in GRP.

By the time The Lead Lads® were appointed, the solution needed to extend beyond replacing the outer weathering layer. The existing build-up was opened, defective materials removed and each bay reconstructed using new structural decking, a vapour-control layer, rigid insulation and a new upper deck before the leadwork was installed.

The new Code 5 coverings were then designed around the rebuilt geometry, bespoke perimeter oversails, stone abutments and additional stainless-steel details suited to the exposed rural setting.

LEAD BAY ROOFS →
WARM CONSTRUCTION LEAD ROOF →
LEAD BAYS TECHNICAL GUIDE →

LOCATION

Scottish Borders

PROGRAMME

Approx. 7 Days

LEAD CODE

Code 5

CONSTRUCTION

Insulated Warm Build-Up

02 — THE FAILURE

The outer covering was only part of the problem

The existing GRP coverings were removed as part of a more substantial reconstruction of both bays.

Opening the roof allowed the insulation, deck and other layers beneath the weathering to be assessed rather than simply concealing the existing build-up beneath another covering.

For this project, the replacement strategy was therefore based on rebuilding the complete assembly from the supporting structure upwards.

The replacement addressed

  • Existing GRP coverings
  • Defective underlying layers
  • Insulation arrangement
  • Vapour-control provision
  • Structural decking
  • Perimeter geometry
  • Stone abutments
  • Exposed-edge restraint

03 — THE REBUILD

Design the roof build-up before the leadwork

The new lead covering forms the outer weathering layer of a deliberately reconstructed roof assembly.

A new lower deck provided structural support. A bituminous vapour-control layer was incorporated within the build-up, followed by rigid PIR insulation and a second plywood deck forming the continuous background for the leadwork above.

This allowed the thermal and moisture-control strategy to be considered separately from the sheet-lead weathering.

The exact roof build-up should always be designed for the individual building. A warm or compact construction should not be inferred simply because lead is used as the final covering.

BS 6915 →
BS EN 12588 →
LSTA Guidelines →

Failed GRP

The original bay roof system before removal and reconstruction.

Rebuilt

New decks, insulation and perimeter construction establish the background for the lead covering.

Code 5 Lead

The finished pair of lead bay roofs following complete reconstruction of the build-up beneath.

04 — THERMAL BUILD-UP

The roof beneath the roof

The visible Code 5 sheet is only the final layer of this construction.

Beneath it sits a sequence of structural deck, vapour-control provision, PIR insulation and top deck designed to create the specified insulated roof assembly.

Each layer has a different purpose. The deck provides support. The vapour-control layer forms part of the moisture strategy. The insulation controls heat flow. The upper board provides the continuous substrate required by the leadwork.

Keeping those functions separate avoids attributing every aspect of roof performance to the lead itself.

05 — EXPOSED LOCATION

Detail the boundaries for the site

The Scottish Borders location added another consideration to the project: exposure.

Projecting bays present several exposed edges and interfaces to wind-driven rain, particularly around perimeter oversails and the junction with stonework.

The reconstructed detail therefore incorporated bespoke timber perimeter sections, stainless-steel restraint and a purpose-made tray detail beneath part of the lead weathering.

The objective was not to make every component heavier, but to strengthen the specific interfaces most exposed to the site conditions.

06 — SIGNATURE DETAIL

The stone abutment and stainless tray

One of the most distinctive details on this project occurs where the bay roof meets the irregular stone elevation.

A bespoke angled interface was required rather than treating the abutment as a conventional flat wall junction.

A 0.7mm stainless-steel tray formed part of the supporting detail before being integrated with the leadwork above.

This gave the project an additional robust layer at a difficult interface while allowing the finished surface to remain visually consistent with the surrounding Code 5 covering.

07 — STRIP + REBUILD

Reconstructing both bays from the structure upwards

  • Existing GRP coverings removed from both bays
  • Defective underlying layers stripped out
  • Previous repair materials removed
  • Existing supporting structure inspected
  • Bay dimensions and abutments rechecked
  • New 18mm plywood lower deck formed
  • Bituminous vapour-control layer installed as specified
  • PIR insulation installed within the new roof build-up
  • Second 18mm plywood deck installed above the insulation
  • Custom timber perimeter oversail formed
  • Stone abutment geometry prepared for bespoke weathering

The finished leadwork follows geometry established by the reconstruction beneath it, making the carpentry and roof build-up fundamental to the finished result.

08 — LEADWORK INSTALLATION

Installing the new Code 5 coverings

  • Code 5 rolled lead sheet set out to both bay roofs
  • Individual pieces sized to suit the reconstructed geometry
  • Lead dressed to the perimeter oversail
  • Custom angled flashing formed at the stone abutment
  • 0.7mm stainless-steel tray incorporated within the bespoke junction
  • Stainless-steel restraint used at appropriate exposed edges
  • Corners and returns bossed where suitable
  • Welded junctions formed where required
  • Abutment flashings integrated with stone and render
  • Fixing arrangement checked for appropriate movement allowance
  • Completed weathering and drainage paths inspected

09 — MATERIALS

More than a lead-sheet replacement

  • Code 5 rolled lead sheet
  • 18mm structural plywood
  • PIR rigid insulation
  • Bituminous vapour-control layer
  • Softwood perimeter sections and mouldings
  • 0.7mm stainless-steel tray
  • Custom stainless-steel clips
  • Compatible non-ferrous fixings
  • Lead welding consumables

CODE 5 LEAD →
18MM PLYWOOD →
ROOF INSULATION →
LEADWORK FIXINGS →
LEAD SIZING + ORDERING →

10 — THE CRAFT

Roof construction and leadwork together

  • Roof strip-out
  • Joinery
  • Deck formation
  • Insulation installation
  • Vapour-control detailing
  • Lead setting out
  • Lead bossing
  • Lead welding
  • Bespoke flashing formation
  • Stainless-steel fabrication
  • Exposed-edge restraint

This project depended as much on understanding the complete roof assembly as on forming the final lead covering.

11 — PROJECT RECORD

Strip.
Insulate.
Rebuild.
Lead.

The Scottish Borders image record documents the change from failed GRP coverings through complete reconstruction of the roof build-ups and into the finished pair of Code 5 lead bays.

It is one of the clearest projects in the archive for showing that successful sheet lead roofing starts beneath the visible surface.

12 — WARM CONSTRUCTION

The lead covering and the thermal build-up are separate systems

A warm or compact roof arrangement typically places the principal insulation above the supporting structure rather than creating a cold void beneath the weathering layer.

That does not mean the lead itself controls condensation.

Moisture performance depends on the complete roof design: insulation continuity, vapour-control provision, junctions, internal conditions and the arrangement of the layers beneath the outer covering all matter.

Above that construction, the lead still requires its own appropriate support, sheet sizing, joints, restraint and movement strategy.

Warm Construction Lead Roof Project →
BS 6915 →
Lead Bays Guide →

13 — GRP TO LEAD

Replacement means more than changing the outer material

The important lesson from this project is not simply that lead replaced GRP.

The improvement came from reconsidering the complete construction: deck, vapour control, insulation, upper substrate, perimeter profile, abutments and final weathering.

Changing one waterproof covering for another while leaving an unsuitable or defective build-up untouched would not address those underlying components.

This makes the Scottish Borders project particularly useful for clients considering the replacement of failed GRP or membrane bay roofs with traditional sheet lead.

Lead Bay Roofs →
Lead Bay Roof Guide →
Discuss a Bay Roof →

14 — WHAT THIS PROJECT SHOWS

Do not ask the new covering to repair the old roof

The strongest lesson from the Scottish Borders bays is that a replacement weathering material cannot compensate for an unsuitable construction beneath it.

These roofs were stripped far enough to reconsider the whole assembly.

The lower deck, vapour-control provision, insulation, upper substrate and perimeter geometry were all established before the first pieces of Code 5 lead were formed.

The lead then performs the task it should perform: providing the durable outer weathering layer to a roof that has already been properly constructed beneath it.

PROJECT TAKEAWAYS

  • Failed outer coverings can justify investigation of the complete roof build-up.
  • Insulation and vapour control should be considered as part of the roof design.
  • The upper deck provides the geometry and support for the lead covering.
  • Exposed locations increase the importance of edges and abutments.
  • Bespoke stainless-steel components can reinforce difficult project-specific details.
  • Code selection depends on the actual sheet dimensions and design.
  • Lead replacement works best when the construction beneath it is resolved first.

15 — FREQUENTLY ASKED

GRP-to-lead bay roof questions

Why was the GRP removed rather than covered with lead?

The project involved reconstruction of the roof build-up beneath the existing coverings. Removing the GRP allowed the underlying layers to be opened, assessed and rebuilt before installing the new lead weathering.

What is a warm roof?

In broad terms, a warm or compact roof arrangement places insulation above the principal structural support so that the supporting construction remains on the warmer side of the insulation. The complete build-up still requires appropriate design of vapour control and junctions.

Does a warm roof eliminate condensation automatically?

No. Condensation risk depends on the complete construction, internal moisture conditions, insulation continuity, vapour-control strategy and junction detailing. The term “warm roof” alone is not a guarantee of performance.

What lead code was used on these bay roofs?

Code 5 rolled lead sheet was used on this project. Other bay roofs should be specified according to their own dimensions, geometry and exposure.

Why was stainless steel incorporated into the detail?

A bespoke stainless-steel tray and custom restraint were used at particular areas of this project to provide a robust supporting solution within the exposed and geometrically difficult interfaces.

Can The Lead Lads undertake projects outside Yorkshire?

Yes. Suitable specialist projects can be considered further afield. This Scottish Borders project was initially assessed using clear photographs, dimensions and project information before the works were undertaken on site.

THE LEAD LADS® / PROJECT ARCHIVE

Failed GRP. Rebuilt roof. Proper leadwork.

The Scottish Borders bays form part of The Lead Lads® archive documenting real applications of rolled lead sheet across bay roofs, warm roof constructions, gutters, dormers, canopies and specialist architectural details.

This project is defined as much by what sits beneath the lead as by the finished sheet: two completely reconstructed insulated roof assemblies protected by new Code 5 lead coverings and bespoke exposed-location details.